What happened
- 90 MW of secured utility power, delivering 61 MW of IT load across five 12.2 MW halls.
- The first 12.2 MW phase is scheduled to enter service in the second quarter of 2028.
- Goodman’s Australian power bank totals 1.3 GW, within a global capital programme approaching A$18 billion.
Why it matters
Phased halls of this size are commissioned one after another. A repeatable, measured flush and fill keeps each phase off the critical path.
SI briefing summarising public reporting by W.Media. Figures are as reported by the source.