News Data centres

Project Ares drops its 2028 first-power date

Energy North is no longer working to June 2028 for its proposed 1 GW off-grid data centre campus in the Northern Territory.

What happened

  • Energy North told Reuters the June 2028 first-power date in its referral was indicative and that it is no longer working to it.
  • Reuters reports the NT Environment Protection Authority suspended its deadline to set assessment requirements on 7 October while it seeks federal advice.
  • The referral describes 1 GW of IT capacity about 52 km north-west of Elliott, with up to 3,000 MWp of solar, up to 16 GWh of battery storage and gas-fired generation.
  • It also proposes taking up to 4 GL a year of groundwater from the Wiso Basin.
Project Ares data centre facility, indicative illustration
Project Ares data centre facility, indicative illustration
Project Ares data centre campus, indicative illustration
Project Ares data centre campus, indicative illustration

Images: Energy North, from its referral to the NT EPA. Indicative illustrations only, not to scale.

Why it matters

Remote, off-grid campuses still have to clear water, land and heritage questions before construction, and federal data centre rules are still being written. Timelines for gigawatt-scale projects outside the major cities remain uncertain.

SI briefing summarising Reuters reporting and the NT EPA referral register. Figures are as stated in the referral.

Talk to us early

Have a project coming up?

Tell us the system and the date. We come back within one business day.

  1. 01At design

    The commissioning scope is right before the specification goes out.

  2. 02In construction

    The flush and fill is programmed off the critical path.

  3. 03At handover

    One certificate. The baseline you keep.