AirTrunk values its Mickleham campus at $4.3 billion

Federal environment documents describe seven buildings at 45 Donnybrook Road, built and commissioned one at a time over about 10 years.

What happened

  • AirTrunk’s preliminary documentation under the EPBC Act (EPBC 2023/09568) opened for public comment on 4 November.
  • The documents describe seven data centre buildings at 45 Donnybrook Road, Mickleham, built and commissioned progressively over about 10 years.
  • An economic assessment in the documents puts the total investment at $4.3 billion and estimates an average of about 1,605 full-time-equivalent construction jobs a year.
  • AirTrunk says the buildings will use dry air chillers, and the site will connect to a new Donnybrook terminal station for a planned 132 kV supply.
  • Comment closes on 18 November, with community drop-in sessions on 17 and 18 November.
AirTrunk Mickleham campus, artist’s impression
AirTrunk Mickleham campus, artist’s impression
AirTrunk Mickleham campus, artist’s impression
AirTrunk Mickleham campus, artist’s impression
AirTrunk Mickleham campus, artist’s impression
AirTrunk Mickleham campus, artist’s impression

Images: AirTrunk. Artist’s impressions only; final design subject to change.

Why it matters

A campus delivered building by building over a decade is a long, staged programme of mechanical installation and commissioning in Melbourne’s north, not a single handover. The state planning decision follows the 28 November Victorian election.

SI briefing summarising AirTrunk’s published project information and EPBC documents. Figures are as stated by AirTrunk.

Talk to us early

Have a project coming up?

Tell us the system and the date. We come back within one business day.

  1. 01At design

    The commissioning scope is right before the specification goes out.

  2. 02In construction

    The flush and fill is programmed off the critical path.

  3. 03At handover

    One certificate. The baseline you keep.