What happened
- AirTrunk’s preliminary documentation under the EPBC Act (EPBC 2023/09568) opened for public comment on 4 November.
- The documents describe seven data centre buildings at 45 Donnybrook Road, Mickleham, built and commissioned progressively over about 10 years.
- An economic assessment in the documents puts the total investment at $4.3 billion and estimates an average of about 1,605 full-time-equivalent construction jobs a year.
- AirTrunk says the buildings will use dry air chillers, and the site will connect to a new Donnybrook terminal station for a planned 132 kV supply.
- Comment closes on 18 November, with community drop-in sessions on 17 and 18 November.



Images: AirTrunk. Artist’s impressions only; final design subject to change.
Why it matters
A campus delivered building by building over a decade is a long, staged programme of mechanical installation and commissioning in Melbourne’s north, not a single handover. The state planning decision follows the 28 November Victorian election.
SI briefing summarising AirTrunk’s published project information and EPBC documents. Figures are as stated by AirTrunk.