What happened
- The second Australian Data Centre Forecast Report from Data Centres Australia and DC Byte puts operational capacity at 1.6 GW across 163 data centres.
- Capacity is forecast to reach 3.9 GW by 2030, up from 3.2 GW in the April edition.
- Melbourne moved 1.2 GW from early stage to committed, against 0.7 GW in Sydney, and its total pipeline now exceeds Sydney’s.
- The share of the pipeline outside the two cities has risen from 19% to 31% over two years.

Image: Data Centres Australia.
Why it matters
The build is spreading: Melbourne and regional sites are taking a larger share of committed capacity, which moves where installation and commissioning work will be needed.
SI briefing summarising the Data Centres Australia media release and report of 30 October 2026. Figures are as stated in the report.