News Data centres

Melbourne’s data centre pipeline overtakes Sydney’s

The second Australian Data Centre Forecast Report puts capacity on track for 3.9 GW by 2030.

What happened

  • The second Australian Data Centre Forecast Report from Data Centres Australia and DC Byte puts operational capacity at 1.6 GW across 163 data centres.
  • Capacity is forecast to reach 3.9 GW by 2030, up from 3.2 GW in the April edition.
  • Melbourne moved 1.2 GW from early stage to committed, against 0.7 GW in Sydney, and its total pipeline now exceeds Sydney’s.
  • The share of the pipeline outside the two cities has risen from 19% to 31% over two years.
Cover of the Australian Data Centre Forecast Report, Issue 2, October 2026
Cover of the Australian Data Centre Forecast Report, Issue 2, October 2026

Image: Data Centres Australia.

Why it matters

The build is spreading: Melbourne and regional sites are taking a larger share of committed capacity, which moves where installation and commissioning work will be needed.

SI briefing summarising the Data Centres Australia media release and report of 30 October 2026. Figures are as stated in the report.

Talk to us early

Have a project coming up?

Tell us the system and the date. We come back within one business day.

  1. 01At design

    The commissioning scope is right before the specification goes out.

  2. 02In construction

    The flush and fill is programmed off the critical path.

  3. 03At handover

    One certificate. The baseline you keep.