What happened
- The Australian Energy Market Commission has made its final rule on access standards for large inverter-based loads, including data centres of 30 MW and above.
- Large loads must ride through certain grid disturbances rather than disconnect.
- Network businesses must assess the combined impact of nearby large loads, and AEMO will develop modelling guidance.
- The rule took effect immediately. Applicants who have already negotiated their access standards have six months to finalise under the old ones.
Why it matters
Ride-through requirements shape how a data centre’s electrical and backup systems are designed and tested before connection, so they now sit inside the commissioning programme for large campuses.
SI briefing summarising the AEMC’s final determination of 12 November 2026.